Supreme Court declines to stay Central Vista project

text_fields
bookmark_border
Supreme Court declines to stay Central Vista project
cancel

New Delhi: The Supreme Court Friday refused to stay any ground work pertaining to the Central Vista project.

Petitioner Rajeev Suri had moved the top court challenging the project on the ground that there is an illegal change in land use and sought directions from the court to stay the project. Petitioner's counsel argued that the environmental clearance committee passed some order, and this matter was considered later, but till then, Solicitor General Tushar Mehta, representing Centre, must assure that no further action will be taken.

A bench comprising Justices A. M. Khanwilkar, Dinesh Maheshwari and Sanjiv Khanna observed: "If the Centre goes ahead when we are seized of this matter, then it will be at their own risk and cost." The bench queried the petitioner's counsel: "When we ask you to argue, then you talk about amending your petition." Mehta contended that the amended petition be filed and the Centre will file a reply. Petitioner's counsel sought that no work on the ground be allowed, which includes the paperwork.

Mehta opposed the argument for stay on the project. "Lordship can say whatever happens will be subject to the orders of the court", argued Mehta. The bench allowed the petitioner to amend the plea, and scheduled the next date of hearing on July 7.

On April 30, the apex court had declined to stay the Central Vista project, estimated to cost Rs 20,000 crore, which seeks to build a new Parliament building and other central government offices in the Lutyens' zone in central Delhi. The plan for the project has been prepared in accordance with India's 75th Independence Day in 2022. The work on the Central Vista is slated for completion by November 2021.

The Central Vista houses iconic buildings like the Parliament House, Rashtrapati Bhavan, the North and South Block buildings, which house important ministries, and also the India Gate. The Centre is proposing to redevelop by constructing a new Parliament house, a new residential complex, which would house the Prime Minister and the Vice President besides several new office buildings.